How to bid electrical jobs: step by step
To bid an electrical job, find work you are qualified to win, get the complete drawings, specs and addenda, count and measure the scope, price labor and material, add overhead and profit, then submit a clear bid form with written exclusions before the deadline. Afterward, follow up and record the result. The steps below explain each one.
1. How do you find electrical jobs to bid on?
Bids reach you through a handful of channels, and most shops use several.
- General contractors you already work with. Repeat customers send invitations to bid. Answering quickly, and bidding the jobs you said you would bid, keeps you on the list.
- Plan rooms and builders exchanges. Local plan rooms, builders exchanges and online bid boards post commercial projects with plans and addenda, usually by membership or fee.
- Public agency bid boards. Cities, counties, school districts and state agencies post public work. Most states run their own procurement portal with its own registration, so search for yours.
- Federal opportunities. SAM.gov Contract Opportunities lists federal solicitations. Anyone can search without an account, and an account adds saved searches and the ability to follow a notice for changes.
- Paid bid-lead services. These collect projects and send alerts. Ask how fresh the leads are and whether the documents come with them.
Whichever channels you use, set up alerts by trade, county and project type so the work finds you.
2. How do you decide which bids are worth pricing?
A careful estimate costs hours. Screen each invitation before you open the plans:
- Qualification. Do you hold the license, bonding capacity and insurance the bid requires? Licensing rules vary by state, and some states regulate bidding itself, so check with your state licensing board before you bid.
- Fit. Is this a type and size of work your crews have done?
- Schedule. Can you staff it alongside the work you already have?
- Customer. Do you know the general contractor or owner, and how they pay?
- Documents. Are the drawings complete enough to price? Thin documents mean more clarifications and more risk.
- Time. Can you finish a careful estimate before the deadline? A rushed number on a job you cannot staff is worse than a pass.
Commercial and public work adds its own screens: bid security, prequalification forms, prevailing wage rules and retainage. The instructions to bidders spell most of them out, so read them first.
3. What documents do you need before you start?
Get the whole package, not just the E sheets:
- Electrical drawings, plus the architectural, mechanical, plumbing and fire protection sheets that carry electrical items
- Specifications, including Division 01 and the electrical, communications and electronic safety sections
- Every addendum
- Instructions to bidders, the bid form and the contract conditions
Read before you count. How to read electrical plans before you start an estimate gives a reading order. Write down every conflict and missing detail as you go, note the deadline for questions, and send them early.
4. How do you do the takeoff?
Takeoff is counting and measuring: devices, fixtures, gear, conduit, wire and feeders. A routine many estimators use is to count one symbol at a time across the whole set, tie fixtures to the fixture schedule, estimate branch runs by a written method, measure feeders from the one-line diagram and check the counts against the panel schedules. The full routine is in How to do electrical takeoffs faster without missing anything.
The order matters. One NECA chapter’s outline of the association’s basic estimating course walks through the same sequence: takeoff, material list, labor units, cost summary, then overhead and profit.
5. How do you price labor and material?
Material. Get current supplier quotes for the big items, such as gear, fixtures, wire and conduit, and use your price book for the small ones. Check hold dates against the likely award date, and confirm tax and freight.
Labor. Quantity times labor unit gives hours, and hours times your burdened labor rate gives cost. The labor units can come from your own history, estimating software or a published reference. See Electrical labor units explained for how to adjust them.
All numbers below are made up to show the arithmetic. Do not use them to bid.
| Item | Quantity | Labor unit (made up) | Hours | Material (made up) |
|---|---|---|---|---|
| Duplex receptacles | 50 | 0.30 hr each | 15 | $600 |
| Light fixtures | 40 | 0.75 hr each | 30 | $4,000 |
| Conduit and wire | 1,000 ft | 5.0 hr per 100 ft | 50 | $2,400 |
| Total | 95 | $7,000 |
At a made-up burdened rate of $80 per hour, labor is 95 x $80 = $7,600, so direct cost is $14,600. A real bid also carries permits, freight, tax, lifts, supervision, temporary power, commissioning and closeout, and any subcontracted work.
6. How do you add overhead and profit?
Overhead is the cost of running your company, and profit is what you earn for taking the risk. Mixing up markup and margin is a common way to price a job too low. The full math is in Electrical estimating markup, overhead and margin without the math traps. Continuing the made-up example:
| Line | Amount (made up) |
|---|---|
| Direct cost | $14,600 |
| Overhead at a made-up 15% of direct cost | $2,190 |
| Cost including overhead | $16,790 |
| Profit at a made-up 10% markup on that cost | $1,679 |
| Price | $18,469 |
Profit of $1,679 on a price of $18,469 is about a 9.1% margin, which is what a 10% markup produces. Show both numbers on your summary so nobody confuses them.
7. What goes on the bid form, and how do you handle exclusions?
Fill in every blank: base bid, alternates, unit prices, addenda numbers, license number and signature. A missing line can disqualify a bid. Then write down what you are not including, in specific terms that match the documents. Some public owners reject bids that take exception to the documents, so ask how clarifications may be submitted. State how long your price holds.
Before you send it, run the checklist in Electrical bid checklist: what to check before you submit, and have a second person review it. If you submit through a portal, upload early.
8. What should you do after you submit?
- Confirm the bid was received, especially for portal and email submissions.
- Stay reachable. A general contractor may call with scope questions or to ask for a revised number.
- Ask for the result. If you lost, politely ask where you were off, but expect that some owners will not share it.
- Log every bid: date, customer, type of work, your price, the winning price if you learn it, and why you think you won or lost.
After a few months the log shows which customers, job types and sizes you actually win. That tells you which bids to chase and which to skip.
9. Can you bid electrical jobs by the square foot?
Not as a bid method. Cost-per-square-foot figures are built for early budgets. RSMeans, for example, describes its square foot models as a tool for conceptual, preliminary estimates in early planning. They do not know how many devices a plan shows, how long the feeders are, what gear the one-line calls for, or how the scope is split between trades.
Square foot numbers are useful as a sanity check after you finish the takeoff. Divide your total by the building area and compare it with your own finished jobs of the same type. A made-up example: your bid works out to $18.50 per square foot, and your last five similar jobs ran from $14 to $17. That does not mean the bid is wrong, but find out why before you submit. Extra gear, a missed addendum or a misplaced decimal are common reasons.
Frequently asked questions
How much should I mark up an electrical bid?
There is no single right number. It depends on your overhead rate and the risk of the job, so work out your overhead first and set profit by risk. The markup guide linked above walks through it.
Can I bid electrical work without a license?
Licensing rules vary by state, and some states treat bidding as contracting. Check with your state licensing board before you submit a bid.
How long does it take to bid an electrical job?
It varies widely with the size of the plan set and your method. Track your hours on each bid so you can plan your week and decide which invitations deserve a full estimate.
What if I miss something after I submit?
Tell the customer promptly and ask how the documents handle bid corrections or withdrawals. Rules differ by owner and by state, so have an attorney review your options if the amount is large.
Where Amptake fits
Amptake is being built to help with step 4. It reads the legend and fixture schedule, counts symbols on the sheet and highlights each one for your review, so you spend less of bid week clicking devices. Deciding which bids to chase, reading the documents, judging branch and feeder runs, pricing, and setting overhead, profit and exclusions all stay with you. Join the waitlist for early access.
This guide is general information, not legal, tax or financial advice. Licensing, bonding and bid rules vary by state and by project.