All guides

Electrical labor units explained: how to use, adjust and check them

Labor units are a part of an electrical estimate that shops often argue about. The number looks precise, but it is only as good as the conditions behind it. Here is what a labor unit is, where published units come from, how to adjust them and how to check them against what your crews actually do.

What a labor unit is

A labor unit is the time it takes to install one unit of an item, usually written in decimal hours. Tables often express them per each, per 100 or per 1,000, so a device might be listed per each, conduit per 100 feet and wire per 1,000 feet.

The arithmetic is simple. Quantity times unit equals hours, and hours times your burdened labor rate equals labor cost. The numbers below are made up to show the math. They are illustrations only and should not be used to bid.

  • 40 devices at a made-up 0.30 hours each is 12 hours.
  • 350 feet of conduit at a made-up 5.0 hours per 100 feet is 3.5 x 5.0, or 17.5 hours.
  • Together that is 29.5 hours. At a made-up burdened cost of $80 per hour, labor is $2,360.

Where published units come from

Several published references exist. One is the NECA Manual of Labor Units, which NECA describes as an experience-based reference for estimating the electrical construction labor needed to install typical electrical and communications systems. NECA says it has been used as an estimating resource since 1923 and updates it in new editions, so confirm which edition you own. We mention it because estimators ask about it. We have no affiliation with NECA and are not endorsing any source. Cost-data books and the units built into estimating software are other options.

Whatever you use, read the front of the book. Training material that quotes the NECA manual describes three columns, normal, difficult and very difficult, for installations that allow progressively less than maximum productivity. It describes the normal column around a typical project: all new materials, complete drawings, a 40-hour week with no scheduled overtime and systems installed 16 feet or less above the floor. Check the current edition for its exact wording.

Also check what a unit includes. Published units may bundle some material handling, layout and clean-up with the installation itself, and sources differ on whether supervision is inside the units or a separate line. Read how your source handles each so you do not count something twice or leave a gap.

Adjust for conditions

A published unit describes a standard condition. Your job may not be standard. Common reasons to adjust:

  • Height. Work above the manual’s standard working height takes longer, and lifts add setup time.
  • Access and congestion. Tight ceilings, crowded shafts and busy mechanical rooms slow the work.
  • Existing buildings. Occupied space, limited work hours, fishing wire through finished walls and protecting finishes all add time.
  • Crew experience. Published units generally assume a skilled, experienced crew. If you will use a more junior crew, plan for it.
  • Schedule. Compressed schedules, shift work and overtime change productivity. Use your own history for how much.
  • Material handling. Long hauls, multiple floors and limited hoist access add time.

You can handle this by choosing a higher column for the whole job or by applying a factor to the tasks that are affected. Pick one method and write down why. Do not apply both for the same condition. If you choose the difficult column because the building is occupied and then add a separate occupied-building factor, you have counted the same difficulty twice.

A made-up example: 12 hours of device work in an occupied building, with a made-up factor of 1.25, becomes 12 x 1.25 = 15 hours.

Calibrate to your own history

No two contractors are the same, and a published unit is an average of someone else’s work. Your job-cost records tell you what your crews actually do.

  1. Pick five to ten finished jobs of a similar type with reasonably clean cost coding.
  2. Pull actual field hours by cost code, such as receptacles, lighting, and conduit and wire, along with the installed quantities.
  3. Divide actual hours by installed quantity to get your actual unit.
  4. Compare it with the unit you estimated.
  5. Find out why any gap exists before you change a number.
  6. Update your units or factors by a documented amount and recheck on a schedule.

A made-up example: you estimated 400 receptacles at 0.30 hours each, or 120 hours. Your records show 150 hours coded to receptacles. Your actual unit is 150 / 400 = 0.375 hours each, which is 25 percent above the estimate (0.375 / 0.30 = 1.25).

Before you adjust, ask whether the gap is real. Hours coded to the wrong cost code, change-order work mixed into base work, rework and a one-off bad site can all make a unit look worse or better than it is. One job is a data point. Several jobs are a trend.

Common mistakes

  • One unit for every condition. The same task costs different amounts in a new warehouse and an occupied hospital wing.
  • Mixing sources. Units from one manual with add-ons from another can double count handling or layout.
  • Stacking factors without thought. Several small factors can add up to a large number nobody can defend.
  • Ignoring labor outside the units. Supervision, mobilization, punch list, commissioning and closeout are often estimated as separate lines.
  • Never closing the loop. If estimated and actual hours are never compared, the units never improve.
  • Assuming your crew matches the book. Your best foreman and your newest apprentice do not install at the same speed.

A short checklist for every estimate

  1. Know what your units include and exclude
  2. State the base conditions you are assuming
  3. Choose a column or factors and write down why
  4. Add labor lines that sit outside the units
  5. Compare estimated and actual hours after every job
  6. Update your units on a schedule, not only when you lose money

Where Amptake fits

Amptake is being built to count symbols from the legend and fixture schedule for your review, then hand the counts to your assemblies and your own labor units. Choosing the conditions, adjusting the units and calibrating them from your job-cost history stay with you. Join the waitlist for early access.

This guide is general information, not legal or professional advice.