How to read electrical plans before you start an estimate
An electrical plan set is a stack of documents that all have to agree with each other, and sometimes they do not. Estimators who read the set in a fixed order catch the disagreements early, before they turn into missed scope. Here is an order that works for most commercial sets. When you are ready to count, the routine in How to do electrical takeoffs faster without missing anything picks up where this one ends.
1. Start with the sheet index
Find the drawing index, usually on the cover or the first general sheet, and check it against the sheets you actually have. Note the issue date of each sheet and make sure every addendum is in your folder. Electrical work also shows up on sheets with other prefixes, so look for fire protection, telecommunications, technology and site sheets too.
Some sets follow the U.S. National CAD Standard. In it, the sheet number starts with the discipline (E for electrical, or two letters such as EP for power and EL for lighting), and the first digit after that is the sheet type: 0 for general sheets such as legends and notes, 1 for plans, 5 for details and 6 for schedules and diagrams. So E-101 and EP101 are both plan sheets. Other firms use their own numbering. Treat the index as the authority, not the numbering.
Also check the scale on each plan sheet against the bar scale or a known dimension. A PDF that was resized in the plan room will not measure correctly.
2. Know the E-series sheet types
- General sheets. Symbol legend, abbreviations, general notes and sometimes code notes.
- Power plans. Receptacles, equipment connections, disconnects and panel locations.
- Lighting plans. Fixtures by type tag, switches, sensors, controls, and emergency and exit fixtures.
- Systems plans. Fire alarm, data, access control and other low voltage. These may sit on the E sheets or on separate sheets.
- One-line diagram. The service, distribution equipment and feeders, with their sizes.
- Schedules. Panel schedules, fixture schedules and equipment connection schedules.
- Details. Mounting heights, equipment pads, typical connections and grounding.
- Demolition plans. On renovation work, what comes out, what stays and what is relocated.
3. Read the legend, abbreviations and notes
Symbols are not fully standard. The same-looking symbol can mean different devices on different sets, so confirm each one against the legend instead of assuming. Note anything unusual.
Then read the general notes slowly. Look for wiring methods, minimum conduit size, device grade, mounting heights, colors, owner-furnished items, work hour limits and the code editions the design cites. If the notes cite a different code edition than your jurisdiction enforces, ask which one governs.
4. Read the schedules
- Fixture schedule. Type tags with description, mounting, voltage, controls and manufacturer. Look for notes on emergency operation and owner-furnished fixtures.
- Panel schedules. Circuit numbers, breaker sizes, loads and what each circuit serves. Check that panel names match the one-line diagram and the plans.
- Equipment schedules. Voltage, phase and connection data for the equipment you are expected to wire, and who furnishes disconnects and starters.
5. Cross-check the specifications
The specs describe products, installation, testing and submittals. The drawings show quantities and locations. You need both. In the CSI MasterFormat system, electrical specs sit in Division 26, communications in Division 27 and electronic safety and security in Division 28, which includes access control, video surveillance and fire alarm. Section numbers have changed between MasterFormat editions, so match sections by title when a spec uses older numbering.
In the 2018 edition, for example, 26 05 19 is low-voltage conductors and cables, 26 05 33 is raceway and boxes, 26 24 00 is switchboards and panelboards and 26 51 00 is interior lighting. Read those sections against the drawings, along with the Division 01 general requirements, which often carry items that affect cost such as work hours, phasing and temporary facilities.
When the drawings and the specs disagree, do not guess. Check the contract’s order of precedence and send a question before the bid questions deadline. If no answer comes, many estimators price the more stringent option and write the assumption into the proposal.
6. Check the other trades’ sheets
Electrical items hide on sheets that are not yours.
- Architectural. Reflected ceiling plans for ceiling types, heights and fixture locations. Door hardware schedules for electrified hardware and access control. Casework plans for power to built-ins.
- Mechanical. Equipment schedules and control diagrams. Confirm who provides starters, drives and disconnects, and who wires the controls.
- Plumbing. Water heaters, pumps and sensor-operated fixtures.
- Fire protection. Sprinkler flow and tamper switches usually need to be wired to the fire alarm system, so make sure that wiring is assigned to someone.
- Civil and site. Utility service, duct banks and site lighting.
Compare each item with your scope split so nothing lands in a gap between trades.
7. Keep a question list as you read
Write down every conflict, missing detail and assumption, with the sheet number. Turn the list into questions to the design team before the deadline in the bid documents, and into clarifications in your proposal. A question found on day one can still be answered. One found the night before the bid cannot.
A short checklist before you count
- Every sheet and addendum matches the index
- Scale confirmed on each plan sheet
- Legend, abbreviations and general notes read
- Fixture, panel and equipment schedules read
- Division 26, 27 and 28 sections read against the drawings
- Architectural, mechanical, plumbing and fire protection sheets checked for electrical items
- Question list started and sent
Where Amptake fits
Amptake is being built to count symbols from the legend and fixture schedule and show every count on the drawing for your review. Reading the whole set, spotting conflicts between sheets and judging the branch and feeder runs stay with you. Join the waitlist for early access.