Electrical estimating markup, overhead and margin without the math traps

Building the direct cost of a job is the part most estimators know well. The trouble often starts with what gets added on top. The words markup, margin and overhead get mixed up, and a mix-up of a few points can turn a planned profit into a loss. Here is how the pieces fit, with the math checked. All dollar figures and percentages below are made up to show the arithmetic.

Markup and margin are not the same number

Markup is profit as a percent of cost. Margin is profit as a percent of price. The dollars are the same, but the base is different.

Say a job costs you $100,000, counting everything including overhead.

  • 25% markup. Price is $100,000 x 1.25 = $125,000. Profit is $25,000. Margin is $25,000 / $125,000 = 20%.
  • 25% margin. Price is $100,000 / (1 - 0.25) = $133,333. Profit is $33,333, which is a markup of 33.3%.

The conversions:

  • margin = markup / (1 + markup)
  • markup = margin / (1 - margin)
Markup on cost Margin on price
10% 9.1%
20% 16.7%
25% 20.0%
30% 23.1%
50% 33.3%

The common error is adding 20% to cost and calling it a 20% margin. You earned 16.7%. Financial statements usually express profit as a percent of revenue, so margin is the number that lines up with your income statement. Pick one term for the shop and print the formula on your estimate summary.

What goes in overhead and what goes in direct cost

Direct job cost exists because of this job: field labor with its burden (payroll taxes, workers compensation and benefits), material, freight, subcontractors, equipment rental, job permits and fees, job-specific bonds and insurance, and temporary power.

Overhead is the cost of running the company that would continue if you had no job today: office rent, office and estimating salaries, owner time, general insurance, vehicles not charged to jobs, software, accounting and marketing.

Some costs are judgment calls, such as project managers, foremen, small tools and trucks. Shops classify them differently. What matters is that you classify them the same way when you calculate the rate and when you bid, or you will count a cost twice or not at all.

How to find your overhead rate

  1. Pull the last 12 months of your profit and loss statement.
  2. Mark every expense line as direct job cost or overhead.
  3. Add up the overhead. If owners work in the business without a normal wage, include a market wage for that work, or profit will look better than it is.
  4. Divide overhead by direct job cost. Some shops divide by revenue instead. Choose one and use it everywhere.
  5. Compare it with next year’s expected volume, because the rate rises when volume falls.

Made-up example: overhead of $450,000 over direct job cost of $3,000,000 is a 15% rate. If direct job cost drops to $2,400,000 and overhead stays the same, the rate is $450,000 / $2,400,000 = 18.75%.

Build the price in layers

Made-up bid:

Line Amount
Direct cost $200,000
Overhead at 15% of direct cost $30,000
Cost including overhead $230,000
Profit at 10% markup on that cost $23,000
Price $253,000

Check the result. Profit is $23,000 / $253,000 = 9.1% margin, which matches 10% markup in the table above. The same $30,000 of overhead is 15% of direct cost but only 11.9% of the price. A rate based on direct cost is applied to cost. A rate based on revenue is a share of the price, so it cannot simply be multiplied by cost. Do not mix the two.

Contingency and allowances are different things

An allowance is an amount stated in the contract documents for something not yet defined, such as owner-selected fixtures. Under the AIA A201-2017 general conditions, an allowance covers the cost of materials and equipment delivered to the site plus taxes. Handling, labor, installation, overhead and profit go in the base price, and the difference is adjusted by change order when actual costs are known. Contracts can change those terms, so read yours.

A contingency is your own money for risk you cannot price, such as unclear details or unknown conditions. Some owners also carry a contingency in their own budget, which is a separate thing. Do not use contingency to cover a known scope gap. Cover that with a clarification or an exclusion.

Bonding, insurance and permits

  • Bonds. The surety sets the premium. Ask your agent how it is figured, and price it per job. If the bid documents require bid security, confirm the form.
  • Insurance. General liability and workers compensation usually live in burden or overhead. If the project has an owner or contractor controlled insurance program, ask what it changes in your price.
  • Permits and fees. Electrical permit and plan review fees vary by jurisdiction. Confirm who pulls the permit and who pays, and check for utility service charges.

Decide where each item lives and keep it there, so you do not charge for it twice or skip it.

Why a flat percent hides risk

One flat markup across every job treats every job as equal. They are not.

  • Labor and material mix. If your overhead tracks field hours, because supervision, project management and insurance scale with them, a flat percent of cost under-recovers on labor-heavy jobs and over-recovers on material-heavy ones. Some shops apply overhead per labor hour or use different percentages for labor and material.
  • Job risk. An occupied building, a tight schedule, unclear drawings, a slow-paying customer or long retainage all deserve more profit than a clean job with a customer you trust.
  • Competition. You may choose to cut profit to win. Do it on purpose, and never cut overhead recovery by accident.

A short checklist for every bid

  1. Direct cost built with a burdened labor rate
  2. Overhead rate reviewed at least once a year and applied on the base it was calculated on
  3. Profit set by job risk, not by habit
  4. Contingency stated and justified, and allowances carried as the documents state them
  5. Bond, insurance and permit lines placed once
  6. Markup and margin both shown on the summary

Where Amptake fits

Amptake is being built to count symbols from the legend and fixture schedule for review and hand the counts to your assemblies and your own labor units, so the quantities behind your direct cost are easy to check. Overhead, profit and contingency stay with you. Join the waitlist for early access.

This guide is general information, not legal, tax or financial advice.