Electrician labor burden rate: how to build a loaded labor rate for bids
Labor burden is the cost of employing an electrician on top of the wage you pay. Payroll taxes, insurance, benefits and paid time off all sit in it. If your estimate prices labor hours at the hourly wage alone, every hour you bid is underpriced. The fix is a loaded labor rate: the wage plus a burden you calculate from your own payroll.
This guide explains what goes into burden, what federal data says about its size, and how to apply it without double counting.
What is labor burden in electrical estimating?
Burden is every labor-related cost that is not the wage itself but still rises and falls with the hours your crew works. A loaded rate is the number you multiply by labor hours from your takeoff. Our guide to electrical labor units covers where those hours come from. This post covers the dollars you attach to each hour.
Burden is not the same as overhead. Burden follows the field employee. Overhead is the cost of running the company: the office, trucks, software and estimators. Mixing them is a common way to count the same dollar twice. See markup, overhead and margin for how overhead is handled.
What costs belong in the burden?
Most contractors include these lines:
- Employer payroll taxes. For 2026, the IRS says the employer pays 6.2% Social Security tax on wages up to a $184,500 wage base and 1.45% Medicare tax with no wage base limit. That is 7.65% on most field wages.
- Unemployment taxes. Federal and state unemployment taxes apply to the employer. State rates depend on your claims history, so use the rate on your own notice.
- Workers’ compensation. The premium depends on your state, your classification codes and your claims record. Ask your insurance agent for the rate that applies to your electricians.
- Health insurance and retirement. Include the employer share of premiums and any employer match.
- Paid time off. Vacations, holidays and sick leave are paid hours that produce no billable work.
- Other labor-related costs. Training, tools allowances and union fringe contributions, if you have them.
If you work under a union agreement or a prevailing wage rule, the fringe amounts are set in the agreement or wage determination. Use those, not an average.
How big is the gap between wages and total pay?
The U.S. Bureau of Labor Statistics (BLS) measures this in its Employer Costs for Employee Compensation release. For June 2026, private industry employers paid $46.89 per hour worked in total compensation. Wages and salaries were $32.82 of that, and benefits were $14.07.
The BLS construction table for June 2026 shows:
| Group (share of total compensation) | Wages and salaries | Total benefits | Legally required benefits |
|---|---|---|---|
| Construction industry | $36.13 (69.5%) | $15.84 (30.5%) | $4.42 (8.5%) |
| Construction, extraction, farming, fishing and forestry occupations | $32.17 (69.0%) | $14.47 (31.0%) | $4.22 (9.0%) |
Divide benefits by wages and the construction industry figure works out to about 44 cents of benefits for every wage dollar. The occupation group works out to about 45 cents.
Treat this as a sanity check, not a rate. The BLS numbers are averages across many workers and employers. The occupation group includes farming and forestry, and the table does not break out electricians. Your own burden can be lower or higher. If your number is far below the averages, check that you have not left out a cost.
How do you calculate your own loaded rate?
Use last year’s payroll records and this year’s insurance quotes. The steps:
- Pick a wage. Use the actual average hourly wage for the crew type you are bidding, such as journeyman or apprentice. For context, the BLS Occupational Outlook Handbook reports a median wage of $30.38 per hour for electricians in May 2025. Local pay and your own pay scale will differ.
- Add each burden item as dollars per paid hour, or as a percent of wages.
- Count productive hours. Paid time off and training hours are paid but not billable. Spread their cost across the hours you can actually bid.
- Divide and review. Total burden cost divided by total wages gives your burden percent. Compare it with last year.
Here is an illustrative example with made-up numbers, not a benchmark. Suppose a journeyman earns $30.00 per hour. Payroll taxes at 7.65% add $2.30. Assume workers’ compensation of 8% adds $2.40, unemployment taxes of 2% add $0.60, health and retirement add $4.00, and paid time off adds $2.00. The loaded rate is $41.30 per hour, a burden of about 38% on the wage. Your inputs will differ, so do not copy these.
Where do estimators go wrong with burden?
- Using the wage as the labor rate. The job loses money on every hour even when the hours are right.
- Applying one rate to every worker. Apprentices, journeymen and foremen carry different wages, and some costs, such as health plans, do not scale with wages.
- Forgetting overtime. If the schedule needs overtime, the premium pay is a job cost. Payroll taxes apply to it, too.
- Never updating the rate. Insurance renewals, wage increases and unemployment tax notices all change the number. Review it at least once a year.
- Counting overhead twice. If office salaries are in overhead, keep them out of burden.
Add a line to your bid review checklist to confirm the loaded rate is the one in the estimate.
Where Amptake fits
Amptake is being built to count the devices and fixtures on a plan set and show every count for your review, which could leave more time to check the figures that sit behind the hours, such as the loaded labor rate. You still set the rates and make the call. Join the waitlist.
This guide is general information, not tax, legal, insurance or accounting advice. Tax rates, insurance premiums and wage rules vary by state and employer, so confirm your numbers with your accountant, insurance agent and payroll provider.