Electrical bid site visit checklist: what to check on a job walk
An electrical bid site visit is your one chance to see what the drawings cannot show. Bring marked-up plans, walk the access routes, power points and equipment locations, photograph everything, and write down what you saw. Then price what you found, and state what you assumed.
This guide covers what to prepare, what to check, and how to keep a record that protects the bid later.
Why does the site visit matter for an electrical bid?
Plans show the design. They do not show a narrow doorway, a low bridge on the delivery route, or a switchboard that is older than the drawings say. An independent electrical estimating consultant writes in EC&M (2020) that some conditions can only be understood in person. He also says to attend even on a new build, to learn who the competition is and to meet possible subcontractors.
Check the specifications first. Some visits are mandatory, so read the instructions to bidders. The same article notes that some facilities, such as correctional facilities, require pre-registration, in some cases 24 hours ahead.
What should you bring?
Prepare before you leave the office. The EC&M article suggests:
- The electrical drawings printed on 11 in. by 17 in. paper, with the items you want to check highlighted.
- A written list of questions about scope and details.
- A camera or phone with a full charge.
- Required personal protective equipment (PPE).
- Business cards to hand out. Also ask for a contact name, so you can arrange a second visit.
Arrive at least 15 minutes before a pre-bid meeting begins, and sign the sign-in sheet. Ask that the attendance record be issued by addendum, so everyone works from the same list. If the specs do not say who answers RFIs, ask, and write down the RFI deadline.
What should you check outside the building?
Walk the path your trucks and crews will take. The article’s list includes:
- Access routes, including low overpasses, bridges and load limits.
- Where the utility connection is, where temporary power could go, and how far it is from the work.
- How hard trenching will be, especially through parking lots, near railroad tracks or near fuel tanks.
- Asphalt cutting and patching, overhead clearances, and the mileage you may need to cover.
Our post on temporary power in an electrical estimate shows where those items land in the price.
What should you check inside the building?
Inside, look at the things that change labor and equipment cost:
- Doorway widths and routes for new equipment, plus roof and elevator access.
- Feeder routing. Where can the new feeder run, and what is in the way?
- Existing equipment you will modify. Note the manufacturer and ratings of switchboards, fire alarm, security and sound systems.
- Rigging needs for heavy gear.
- Crawl spaces and whether anyone can reach them.
- Hazardous materials in demolition scope. The article names PCB ballasts and transformers, and fluorescent lamps. See the note below.
If you remove old lighting, ask who owns the disposal question. The U.S. EPA’s fact sheet on PCBs in fluorescent light ballasts (2020) says any fluorescent light ballast made before July 2, 1979 may contain PCBs. It also says the potting material in those ballasts frequently has PCB concentrations over 50 ppm. Ballasts made from July 1978 to July 1998 that do not contain PCBs were required to carry a “No PCBs” label under 40 CFR 761.40(g).
For you, that means three things on the walk. Record the ballast age and labels where you can see them. Ask the owner whether a hazardous materials survey exists. Write into your bid who handles and pays for abatement or disposal. The rules are detailed, so confirm them with the owner, your disposal contractor or a qualified professional.
How should you use photos and notes?
Photos only help if you can find them later. The article recommends photographing building entrances, floor changes, room names, access roads, excavation paths, rigging areas and overhead clearances. It also suggests marking on your drawings where you stood and which way each photo faces.
- 1Read the specs for visit rules
- 2Print and mark the drawings
- 3Walk outside, then inside
- 4Photograph and mark each location
- 5Price findings, write assumptions
Add the names of the people you spoke with and the date. If you learn something that changes scope, put it in your written clarifications. Our post on electrical bid exclusions and clarifications covers where to write it.
Why does a written record of existing conditions matter?
If conditions differ from what the bid documents showed, a record of what you saw can matter. Public contracts show the idea. The federal differing site conditions clause, FAR 52.236-2, covers “subsurface or latent physical conditions at the site which differ materially from those indicated in this contract” and “unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered…” It requires written notice “promptly, and before the conditions are disturbed,” and provides for an equitable adjustment when its conditions are met.
That clause applies to federal contracts. Your contract may say something different, and private contracts may. Read the site and conditions language in yours, and ask a construction attorney how it applies. Either way, dated photos and notes made before work starts are easier to rely on than memory.
What do you do after the walk?
Soon after the walk, while it is fresh:
- Sort photos by area and label them.
- Compare what you saw to the plan set and flag differences.
- Add line items for access, rigging, demolition and temporary power you did not see on the plans.
- Send RFIs for anything unclear, before the RFI deadline.
- Write assumptions into your clarifications.
- Add the findings to your bid review. Our electrical bid review checklist is a good place to confirm nothing slipped.
Where Amptake fits
Amptake is being built to count devices and fixtures on a plan set, show each count on the drawing and build a bid from your own labor units and supplier pricing. The site visit stays your job, because only you can see the building. Join the waitlist for early access.
This article is general information for estimators, not engineering, legal or environmental advice. Check your contract, local requirements and hazardous materials rules with a qualified professional before you bid.