Electrical equipment lead times: how to protect a bid from long waits
Long equipment lead times are a bid problem, not just a purchasing problem. If your price assumes gear arrives when the schedule says, and it arrives months later, you carry the idle crew, the extended general conditions and the price change. The fix is to ask for a real lead time before you bid, write it into the proposal, and say what happens if the date moves.
How long are lead times for electrical gear?
Published numbers vary a lot by equipment type, size and year, so treat any single figure as a range to check, not a promise.
The best government figures are for distribution transformers. The Department of Energy’s Supply Chain and Market Analysis page says lead times went from three to six months in 2019 to 12 to 30 months in 2023, and calls 2023 the latest available data. A National Renewable Energy Laboratory report, Major Drivers of Long-Term Distribution Transformer Demand (February 2024), says utilities were seeing waits of up to 2 years, a 4x increase on lead times before 2022. It also says prices had gone up by as much as 5 to 6 times in the past 2 years.
- 20193 to 6 months
- 202312 to 30 months (latest data DOE lists)
Distribution transformers bought by utilities. Your own supplier's quote may differ.
Source energy.gov
For switchgear and other gear, public data is thin. An article from a contractor, Terrapin Construction Group, lists medium-voltage switchgear at 52 to 72 weeks for 5 kV/15 kV metal-enclosed units and pad-mount transformers at 40 to 65 weeks. It says the figures come from its own manufacturer slot reservations and project data. That is one company’s view, and the article is not consistent with itself in places, so use it to see how big the gap can be, not as a quote.
The takeaway is simple: a lead time copied from an old price sheet may no longer be true. Ask the supplier today.
Which items on a bid are most at risk?
Lead times matter most for items that are large, custom or made to order. On a typical commercial job, check:
- Switchgear, switchboards and distribution panels
- Dry-type and pad-mount transformers
- Generators and automatic transfer switches
- Specialty lighting and lighting control panels
- Fire alarm and other systems from a single approved manufacturer
Branch wire, conduit, boxes and standard devices usually come from stock, but check the big jobs and any special order. The risk is the one item that sets the date for energizing the building.
What does a late delivery cost you?
A late delivery does not only change the material price. Think through the pieces:
- Crew time. People wait, move to other work or come back, and each move costs hours.
- Extended general conditions. Supervision, trailers and equipment run longer.
- Price changes. A quote may expire before you place the order.
- Schedule pressure. Other trades may be ready and you are the hold-up, which can bring delay claims.
- Temporary power. If the permanent service is late, the job may need temporary power for longer. See our post on temporary power in an electrical estimate.
None of this shows up in a material takeoff. It lives in your assumptions and your proposal.
How do you check lead time before you bid?
Add a short lead-time step to your bid review. A simple order of work:
- 1List long-lead items
- 2Get written lead times
- 3Compare to the schedule
- 4Put dates and limits in the bid
In practice:
- Ask for a written lead time and a quote validity date. A verbal “about 30 weeks” is hard to defend later.
- Ask what the lead time starts from. It may run from approved submittals, not from the purchase order.
- Compare it to the schedule. Work backward from the date power or equipment is needed. Include submittal review time, which you do not control.
- Look for alternates. The Terrapin article suggests naming acceptable alternate manufacturers and comparing earliest delivery. Check that the specification and the engineer allow substitutions before you price one.
- Ask about reserving a production slot. The same article says that without a reserved slot the wait can grow by 8 to 16 weeks, and that holding a slot can take 10 to 30% of the equipment cost up front. Ask what a hold costs you.
What should the proposal say?
Put the assumptions where the general contractor can see them. Illustrative wording choices (adapt them to your own job and have your contract reviewed as needed):
- “Pricing is based on switchgear delivery of [number] weeks from approved submittals, per the supplier quote dated [date].”
- “Equipment pricing is valid for [number] days. Price changes after that date are not included.”
- “Schedule relief and cost are requested if approved submittals are returned later than [date].”
Also check the contract itself. Some contracts handle material price changes with an escalation clause. Others make you hold the price. If the contract does not let you pass on a price change, either price the risk or decide whether to bid. Our posts on protecting bids from material price swings and bid exclusions and clarifications go through the options.
Should long lead times change your bid or no-bid choice?
They can. A job with a tight energization date and a single-source switchboard is riskier than one with flexible dates and standard gear. Put lead time on your scorecard next to the usual items. Our guide to the electrical bid or no-bid decision shows how to do that.
If a general contractor will not accept any schedule or price language, you can also bid with the risk priced in, ask the general contractor to buy the long-lead items directly, or pass.